Edvard Grieg Electrode boilers shipped
16. Feb 2022

Edvard Grieg Electrode boilers shipped

In June 2020 PARAT Halvorsen was awarded the contract to supply 2 x 17MW High Voltage Electrode Boilers for Lundin Energy Norway's platform Edvard Grieg.



Edvard Grieg Electrode boilers shipped

PARAT Electrode boilers for Edvard Grieg have been shippedThe Electrode Boiler skids was lifted onboard the MV Island Commander before its journey to Edvard Grieg in the North Sea. (Photo: PARAT Halvorsen)


PARAT has designed and manufactured a complex EX-certified boiler package for outdoor installation, and 31.01.2022 the delivery protocol was signed by PARAT Halvorsen and Aker Solution.

Aker Solution has delivered a structure that already has been installed at Edvard Grieg. All is ready for the boiler package to be installed on top of the new deck.

Cranes and supply vessel arrived at PARAT's facilities, and the boiler package was steady lifted onboard. From PARAT's quay the boiler package will be transported directly out to the platform and lifted onboard to the designated area.

Later in 2022 when the power from shore is ready, the heating medium system on Edvard Grieg will be heated by 'Clean Technology' from PARAT Halvorsen in Flekkefjord.


PARAT Electrode boilers for Edvard Grieg have been shipped

PARAT Electrode boilers for Edvard Grieg are ready for delivery PARAT Electrode boilers for Edvard Grieg are ready for delivery

More information

PARAT Halvorsen AS

Product Request

Sähköposti: sales@parat.no

PARAT MEH Offshore

Download datasheet
pdf



Meet us: All-Energy 15. - 16. May 2024 in Glasgow, Scotland
Meet us: Energia 22. - 24. October 2024 in Tampere, Finland

Uutiset

News archive